[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118334,789,1,"单选题","某工程主体结构混凝土工程量约为3200立方米，预算单价为500元每立方米，计划四个月内均衡完成，实际采购价560元每立方，施工至第二个月底，实际完成混凝土工程量为1800立方米，运用赢得值法，可分析的该工程进度偏差SV为()万元",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-1.8",false,{"key":16,"text":17,"correct":14},"B","1.8",{"key":19,"text":20,"correct":14},"C","-10",{"key":22,"text":23,"correct":24},"D","10",true,"2021\u002F2020教材P112页 进度偏差(SV)=已完工作预算费用(BCWP)—计划工作预算费用(BCWS)工程均衡完成，则每月计划完成工程量=3200\u002F4=800立方米，施工至第二个月底，累计计划完成工程量为1600立方米，则有，bcwp=1800×500。bcws=1600×500，故进度偏差sv=bcwp-bcws=1800×500-1600×500=100000",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]