[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118333,789,1,"单选题","关于应用曲线法进行施工进度偏差分析的说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划工作预算费用曲线-已完工作实际费用曲线间的两项参数之差表示费用偏差",false,{"key":16,"text":17,"correct":14},"B","计划工作预算费用曲线-已完工作预算费用曲线间的两项参数之差表示费用偏差",{"key":19,"text":20,"correct":14},"C","已完工作实际费用曲线-已完工作预算费用曲线间的两项参数之差表示进度偏差",{"key":22,"text":23,"correct":24},"D","已完工作预算费用曲线-计划工作预算费用曲线间的两项参数之差表示进度偏差",true,"2021\u002F2020教材P112页 费用偏差CV=已完工作预算费用BCWP-已完工作实际费用ACWP； 进度偏差SV=已完工作预算费用BCWP-计划工作预算费用BCWS；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]