[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118331,789,1,"单选题","将项目总施工成本分解到单项工程和单位工程中，再进一步分解为分部工程和分项工程，该种施工成本计划的编制方式属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按施工成本组成编制",false,{"key":16,"text":17,"correct":18},"B","按项目组成编制",true,{"key":20,"text":21,"correct":14},"C","按工程进度编制",{"key":23,"text":24,"correct":14},"D","按合同结构编制","2021\u002F2020教材P106页 按施工成本组成分解的施工成本计划是将成本分解为人工费、材料费、施工机械使用费、措施费和间接费，故选项A不正确； 按工程进度编制的成本计划应与项目的进度联系起来，故C不正确； 施工成本计划的编制方式中不包括“按合同结构编制”的成本计划，故选项D也不正确； 将项目总施工成本分解到单项工程和单位工程中，再进一步分解为分部工程和分项工程，应属于“按项目组成”编制施工成本计划的方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]