[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118330,789,1,"单选题","某施工项目按人工费、材料费、施工机械使用费、措施费和间接费对施工成本计划进行了编制，这种编制方法属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按施工成本组成编制施工成本计划",true,{"key":16,"text":17,"correct":18},"B","按子项目组成编制施工成本计划",false,{"key":20,"text":21,"correct":18},"C","按工程进度编制施工成本计划",{"key":23,"text":24,"correct":18},"D","以上三种方法的综合运用","2021\u002F2020教材P106页 施工成本可以按成本组成分解为人工费、材料费、施工机械使用费、企业管理费等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]