[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118328":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118328,789,1,"单选题","绘制S形曲线这种编制成本计划的方法是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按施工成本组成编制",false,{"key":16,"text":17,"correct":14},"B","按子项目组成和按工程进度相结合编制",{"key":19,"text":20,"correct":14},"C","按工程进度编制",{"key":22,"text":23,"correct":24},"D","按施工成本组成和工程进度相结合编制",true,"2021\u002F2020教材P108页 S形曲线是利用时间成本曲线表示竖向表示施工成本，横向表示工程进度。如图2Z102063-4时间成本累计曲线（S形曲线）",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]