[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118321":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118321,789,1,"单选题","某工程施工至2014年12月底，经分析，已完工作预算费用为150万元，已完工作实际费用为165万元，计划工程预算费用为185万元，则该工程的进度偏差为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超前15万元",false,{"key":16,"text":17,"correct":18},"B","延误35万元",true,{"key":20,"text":21,"correct":14},"C","超前20万元",{"key":23,"text":24,"correct":14},"D","延误30万元","2021\u002F2020教材P112页 进度偏差(SV)=已完工作预算费用(BCWP)－计划-工作预算费用(BCWS)=150－185=-35万元，当进度偏差SV为负值时，表示进度延误，实际进度落后于计划进度；当进度偏差SV为正值时，表示进度提前，实际进度快于计划进度。故该工程的进度偏差延误35万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]