[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118317,789,1,"单选题","施工成本计划是根据施工项目的具体情况制定的施工成本控制方案，包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预定的具体成本目标和有可能出现的成本偏差",false,{"key":16,"text":17,"correct":14},"B","可能的工程变更和对变更的控制措施",{"key":19,"text":20,"correct":21},"C","预定的具体成本目标和实现控制目标的措施",true,{"key":23,"text":24,"correct":14},"D","预定的经济效益目标和实现经济效益目标的手段","2021\u002F2020教材P109页 施工成本计划是根据施工项目的具体情况制定的施工成本控制方案，既包括预定的具体成本控制目标，又包括实现控制目标的措施和规划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]