[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118314":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118314,789,1,"单选题","某施工承包企业将其承接的高速公路项目的目标总成本分解为桥梁、隧道、道路工程成本等子项，并编制相应的成本计划，这是按()分解的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本组成",false,{"key":16,"text":17,"correct":18},"B","项目组成",true,{"key":20,"text":21,"correct":14},"C","工程类别",{"key":23,"text":24,"correct":14},"D","工程性质","2021\u002F2020教材P107页 二、按施工项目组成编制施工成本计划的方法。大中型工程项目通常是由若干单项工程构成的，而每个单项包括多个单位工程，每个单位工程又是由若干个分部分项工程所构成。因此首先要把项目总施工成本分解到单项工程和单位工程中，再进一步分解到分部工程和分项工程中。选B，按项目组成分解的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]