[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118310,789,1,"单选题","某钢门窗安装工程，工程进行到第三个月末时，已完工作预算费用为35万元，已完工作实际费用为30万元，则该项目的成本控制效果是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用偏差为-5万元，项目运行超出预算",false,{"key":16,"text":17,"correct":18},"B","费用偏差为5万元，项目运行节支",true,{"key":20,"text":21,"correct":14},"C","费用偏差为5万元，项目运行超出预算",{"key":23,"text":24,"correct":14},"D","费用偏差为-5万元，项目运行节支","2021\u002F2020教材P112页 费用偏差一已完工作预算费用一已完工作实际费用，当费用偏差为负值时，即表示项目运行超出预算费用；当费用偏差为正值时，表示项目运行节支，实际费用没有超出预算费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]