[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118306,789,1,"单选题","某土方工程某月计划开挖9000m3，合同单价30元／m3，到月底实际完成土方量为9500m3，实际单价为28元／m3，则该工程的费用偏差(cv)为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.9",true,{"key":16,"text":17,"correct":18},"B","-1.9",false,{"key":20,"text":21,"correct":18},"C","1.4",{"key":23,"text":24,"correct":18},"D","-1.5","2021\u002F2020教材P112页 已完工作预算费用（BCWP）=已完成工作量×预算单价；已完工作实际费用（ACWP）=已完成工作量×实际单价；费用偏差（CV）=已完成工作预算费用（BCWP）-已完工作实际费用（ACWP）。费用偏差=9500×30-9500×28=1.9。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]