[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118304":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118304,789,1,"单选题","某工程主体结构混凝土工程量约3200m3，预算单价550元\u002Fm3，计划4个月内均衡完成。开工后，混凝土实际采购价格为560元／m3。施工至第二个月底，实际完成混凝土工程量1800m3。运用赢得值法，可分析得到该工程的进度偏差sv为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-1.8",false,{"key":16,"text":17,"correct":14},"B","1.8",{"key":19,"text":20,"correct":14},"C","-11",{"key":22,"text":23,"correct":24},"D","11",true,"2021\u002F2020教材P112页 根据题意，工程均衡完成，则每月计划完成工程量=3200\u002F4=800m3。施工至第二个月月底，累计计划完成工程量为1600m3，则已完工作预算费用BCWP=已完成工作量×预算单价=1800×550=990000元，已完工作实际费用ACWP=已完成工作量×实际单价=1800×560=1008000元，计划工作预算费用BCWS=计划工作量×预算单价=1600×550=880000元。故进度偏差SV=BCWP-BCWS=990000-880000=110000元，选项D正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]