[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118303,789,1,"单选题","某地下工程施工合同约定，计划3月份完成混凝土工程量500m3，合同单价为600元\u002Fm3。该工程3月份实际完成的混凝土工程量为400m3，实际单价700元\u002Fm3。至3月底，该工程的费用绩效指数（CPI）为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.800",false,{"key":16,"text":17,"correct":18},"B","0.857",true,{"key":20,"text":21,"correct":14},"C","1.167",{"key":23,"text":24,"correct":14},"D","1.250","2021\u002F2020教材P112页 费用绩效指数CPI=已完工作预算费用BCWP\u002F已完工作实际费用ACWP-400×600\u002F400×700=0.8570已完工作预算费用BCWP=已完成工作量×预算单价已完工作实际费用ACWP=已完成工作量×实际单价",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]