[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118299,789,1,"单选题","某土方工程项目，按施工进度计划安排，工程进展到3个月底时计划完成土方工程量1000m3，挖土方的合同单价50元\u002Fm3；当工程实际进展到3月底时，完成土方工程量1200m3，挖土方的实际单价60元\u002Fm3，则该土方工程到3月底的成本偏差与进度偏差分别为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-1.2,-1.2",false,{"key":16,"text":17,"correct":18},"B","-1.2,1.0",true,{"key":20,"text":21,"correct":14},"C","1.2，-1.0",{"key":23,"text":24,"correct":14},"D","1.2,1.2","2021\u002F2020教材P112页 1.费用偏差费用偏差=已完工作预算费用-已完工作实际费用=50×1200-60×1200=-1.2万元；2.进度偏差=已完工作预算费用-计划工作预算费用=50×1200-50×1000=1万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]