[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118296,789,1,"单选题","进行施工成本控制，工程实际完成量、成本实际支付等信息主要是通过（）获得。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度报告",true,{"key":16,"text":17,"correct":18},"B","施工成本计划",false,{"key":20,"text":21,"correct":18},"C","工程承包合同",{"key":23,"text":24,"correct":18},"D","施工组织设计","2021\u002F2020教材P109页 3、进度报告进度报告提供了每一时刻工程实际完成量，工程施工成本实际支付情况等重要信息。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]