[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118290":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118290,789,1,"单选题","下列各项中，（）既是施工成本控制的依据．又是施工成本控制的指导文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",false,{"key":16,"text":17,"correct":18},"B","施工成本计划",true,{"key":20,"text":21,"correct":14},"C","进度报告",{"key":23,"text":24,"correct":14},"D","施工组织设计","2021\u002F2020教材P109页 施工成本计划是根据施工项目的具体情况制定的施工成本控制方案，既包括预定的具体成本控制目标，又包括实现控制目标的措施和规划，是施工成本控制的指导文件。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]