[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118287,789,1,"单选题","赢得值法的三个基本参数不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划工作实际费用",true,{"key":16,"text":17,"correct":18},"B","计划工作预算费用",false,{"key":20,"text":21,"correct":18},"C","已完工作实际费用",{"key":23,"text":24,"correct":18},"D","已完工作预算费用","2021\u002F2020教材P112页 赢得值法三个基本参数：已完工作预算费用，计划工作预算费用，已完工作实际费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]