[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118285":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118285,789,1,"单选题","下列施工成本纠偏措施中，能压缩已经超支的费用而不损害其他目标的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","减少工程范围",false,{"key":16,"text":17,"correct":14},"B","降低设计标准",{"key":19,"text":20,"correct":21},"C","提高生产效率",true,{"key":23,"text":24,"correct":14},"D","增加替换材料","2021\u002F2020教材P114， 减少工程范围的成本纠偏措施，将影响工程功能；降低设计标准，将影响工程功能和质量；增加替换材料，将影响工程功能和质量；而提高生产效率，既压缩超支的费用，又不损害其他目标。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]