[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118284,789,1,"单选题","下列关于施工成本控制中获得成本信息的说法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","通过工程承包合同获取预定的具体成本控制目标、实现控制成本的措施等信息",false,{"key":16,"text":17,"correct":14},"B","通过施工成本计划获取将要发生工程量、支付情况等信息",{"key":19,"text":20,"correct":21},"C","通过进度报告获取工程实际完成量、成本实际支出等信息",true,{"key":23,"text":24,"correct":14},"D","通过施工组织设计获取工程预算收入、实际成本等信息","2021\u002F2020教材P109页 进度报告提供了每一时刻工程实际完成量，工程施工成本实际支付情况等重要信息。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]