[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118282,789,1,"单选题","某打桩工程施工至第二个月底，出现了工程的费用偏差小于0，进度偏差大于0的状况。则至第二个月底中该打桩工程的已完工作实际费用(ACWP)、计划工作预算费用(BCWS)和已完工作预算费用(BCWP)的关系可表示为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","BCWP>ACWP>BCWS",false,{"key":16,"text":17,"correct":14},"B","BCWS>BCWP>ACWP",{"key":19,"text":20,"correct":21},"C","ACWP>BCWP>BCWS",true,{"key":23,"text":24,"correct":14},"D","BCWS>ACWP>BCWP","2021\u002F2020教材P112页 按赢得值法，费用偏差CV=BCWP-ACWP；进度偏差SV=BCWP-BCWS。若CV BCWP；SV>0，则BCWP大于BCWS。故有ACWP＞BCWP＞BCWS。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]