[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118281,789,1,"单选题","某打桩工程合同约定，第一个月计划完成工程桩120根，单价为1.2万元／根。至第一个月底，经确认的承包商实际完成的工程桩为110根，实际单价为1.3万元／根。则在第一个月度内，该打桩工程的计划工作预算费用(BCWS)为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","132",false,{"key":16,"text":17,"correct":14},"B","143",{"key":19,"text":20,"correct":21},"C","144",true,{"key":23,"text":24,"correct":14},"D","156","2021\u002F2020教材P112页 BCWS是赢得值法中的参数之一，是按计划工作量乘以预算价格而得，故为120×1.2=144万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]