[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118278,789,1,"单选题","以下关于费用绩效的说法，正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当费用绩效指数SPI小于1时，表示进度延误，即实际进度比计划进度拖后",false,{"key":16,"text":17,"correct":14},"B","当费用绩效指数SPE大于1时，表示进度提前，即实际进度比计划进度快",{"key":19,"text":20,"correct":14},"C","当费用绩效指数CPI小于1时，表示进度提前，即实际进度比计划进度快",{"key":22,"text":23,"correct":24},"D","当费用绩效指数CPI大于1时，表示节支，即实际费用低于预算费用",true,"2021\u002F2020教材P112页 3.费用绩效指数（CPI）费用绩效指数=已完成工作预算费用\u002F已完成工作实际费用。当费用绩效指数CPI＞1时，表示节支，及实际费用低于预算费用。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]