[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118277,789,1,"单选题","项目施工准备所需的施工预算成本计划是指（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竞争性成本管理",false,{"key":16,"text":17,"correct":14},"B","指导性成本管理",{"key":19,"text":20,"correct":21},"C","实施性成本管理",true,{"key":23,"text":24,"correct":14},"D","战略性成本管理","2021\u002F2020教材P102页 三、实施性计划成本即项目施工准备阶段的施工预算成本计划，它以项目实施方案为依据，落实项目经理责任目标为出发点，采用企业的施工定额，通过施工预算的编制而形成的实施性施工成本计划。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]