[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118276,789,1,"单选题","作为施工成本控制的重要依据，工程实际完成量和成本实际支出等信息主要是从（）中获取的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业务核算报告",false,{"key":16,"text":17,"correct":14},"B","施工组织设计",{"key":19,"text":20,"correct":21},"C","工程进度报告",true,{"key":23,"text":24,"correct":14},"D","工程变更报告","2021\u002F2020教材P109页 因为工程实际完成量、成本实际支出等信息，反映的是工程进展的实际状况，由进度报告反映，所以选C。业务核算报告、施工组织设计和工程变更报告分别反映综合性经济指标、施工的计划信息和工程变更情况等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]