[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118275,789,1,"单选题","某项目编制施工成本计划时，先将成本按分部分项工程进行了划分，又将各分部分项工程成本按人工费、材料费和施工机械使用费等分开编制，这种编制方法属于()。 A.按施工成本组成编制施工成本计划",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按项目组成编制施工成本计划",false,{"key":16,"text":17,"correct":14},"B","按工程进度编制施工成本计划",{"key":19,"text":20,"correct":14},"C","上述",{"key":22,"text":23,"correct":24},"D","B两种方法的综合运用",true,"2021\u002F2020教材P106页 先将成本按照分部分项工程进行划分是按项目组成编制的，然后按照人工费、材料费、施工机械使用费进行编制是按照施工成本组成编制施工成本计划的。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]