[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118273":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118273,789,1,"单选题","以合同标书为依据，依据企业的预算定额标准制定的设计预算成本计划属于（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竞争性成本计划",false,{"key":16,"text":17,"correct":18},"B","指导性成本计划",true,{"key":20,"text":21,"correct":14},"C","实施性成本计划",{"key":23,"text":24,"correct":14},"D","按成本分解的成本计划","2021\u002F2020教材P101页 即选派项目经理阶段的预算成本计划，是项目经理的责任成本目标。它是以合同标书为依据，按照企业的预算定额标准制定的设计预算成本计划，且一般情况下只是确定责任总成本指标。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]