[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118272,789,1,"单选题","某工程项目有4800m3的土方开挖施工任务，交由某分包商承担，计划在6个月内完成，每月计划完成工程量为800m3，预算单价为580元／m3。开工后发现实际单价为600元／m3。工程进行了3个月，累计完成工程量3000m3。运用赢得值法分析，至第3个月底的进度偏差位为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-34.8",false,{"key":16,"text":17,"correct":14},"B","-6",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","34.8",true,"2021\u002F2020教材P112页 进度偏差(SV)=已完工作预算费用(BCWP)—计划工作预算费用(BCWS)。代入计算：进度偏差=580×3000-580×2400=34.8万@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]