[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118271":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118271,789,1,"单选题","采用赢得值法分析成本偏差得到的结果如下图所示，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度滞后，费用节支",false,{"key":16,"text":17,"correct":14},"B","进度提前，费用节支",{"key":19,"text":20,"correct":21},"C","进度提前，费用超支",true,{"key":23,"text":24,"correct":14},"D","进度滞后，费用超支","2021\u002F2020教材P112页 1.费用偏差CV(CostVariance) 费用偏差(CV)=已完工作预算费用(BCWP)-已完工作实际费用(ACWP) 当费用偏差(CV)为负值时，即表示项目运行超出预算费用；当费用偏差(CV)为正值时，表示项目运行节支，实际费用没有超出预算费用。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]