[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118270,789,1,"单选题","施工成本管理的五个环节的任务顺序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析—计划—控制—核算—核算",false,{"key":16,"text":17,"correct":18},"B","计划—控制—核算—分析—考核",true,{"key":20,"text":21,"correct":14},"C","分析—计划—控制—核算—考核",{"key":23,"text":24,"correct":14},"D","计划—控制—考核—分析—核算","2021\u002F2020教材P98页 施工成本管理的任务主要包括：1）施工成本计划；2）施工成本控制；3）施工成本核算；4）施工成本分析；5）施工成本考核。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]