[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118267,789,1,"单选题","下列不属于工程项目施工成本的直接成本的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人工费",false,{"key":16,"text":17,"correct":14},"B","材料费",{"key":19,"text":20,"correct":21},"C","工具用具使用费",true,{"key":23,"text":24,"correct":14},"D","施工措施费","2021\u002F2020教材P97页 直接成本是指施工过程中耗费的构成工程实体或有助于工程实体形成的各项费用支出，其是可以直接计入工程对象的费用，包括人工费、材料费、施工机械使用费和施工措施费等。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]