[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118262":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118262,789,1,"单选题","通过加强施工定额管理和施工任务单管理,控制活劳动和物化劳动的消耗。这属于施工成本管理措施的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术措施",false,{"key":16,"text":17,"correct":18},"B","组织措施",true,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","合同措施","2021\u002F2020教材P100页 组织措施是从施工成本管理的组织方面采取的措施。比如加强施工定额管理和施工任务单管理,控制活劳动和物化劳动的消耗等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]