[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118256,789,1,"单选题","成本偏差的控制，( )是关键，要针对偏差发生原因，采取切实措施，加以纠正。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","纠偏",false,{"key":16,"text":17,"correct":18},"B","分析",true,{"key":20,"text":21,"correct":14},"C","核算",{"key":23,"text":24,"correct":14},"D","控制","2021\u002F2020教材P99页 施工成本分析：成本偏差的控制，分析是关键，纠偏是核心。要针对偏差发生原因，采取切实措施，加以纠正。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]