[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118254,789,1,"单选题","编制施工成本控制工作计划、确定合理详细的工作流程是( )的内容之一。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同措施",false,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":14},"C","技术措施",{"key":22,"text":23,"correct":24},"D","组织措施",true,"2021\u002F2020教材P100页 1.组织措施：组织措施的另一方面是编制编制施工成本控制工作计划，确定合理详细的工作流程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]