[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118253":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118253,789,1,"单选题","结合项目的施工组织设计及自然地理条件，降低材料的库存成本和运输成本，属于施工成本管理的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术措施",true,{"key":16,"text":17,"correct":18},"B","组织措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","2021\u002F2020教材P100页 2.技术措施施工过程中降低成本的技术措施，包括如进行技术经济分析，确定最佳的施工方案。结合施工方法，进行材料使用的比选，在满足功能要求的前提下，通过代用、改变配合比、使用添加剂等方法降低材料消耗的费用。确定最合适的施工机械、设备使用方案。结合项目的施工组织设计及自然地理条件，降低材料的库存成本和运输成本。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]