[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118252":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118252,789,1,"单选题","落实施工成本管理的组织机构和人员，属于施工成本管理措施中的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","合同措施",{"key":23,"text":24,"correct":18},"D","经济措施","2021\u002F2020教材P100页 落实施工成本管理的组织机构和人员，属于施工成本管理措施中的组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]