[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118251":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118251,789,1,"单选题","施工成本的核算对象一般是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单项工程",false,{"key":16,"text":17,"correct":18},"B","单位工程",true,{"key":20,"text":21,"correct":14},"C","分部工程",{"key":23,"text":24,"correct":14},"D","分项工程","2021\u002F2020教材P99页 施工成本的核算对象一般是单位工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]