[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118250,789,1,"单选题","通过生产要素的优化配置，有效控制实际成本，属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","2021\u002F2020教材P100页 描述组织措施第二段中明确指出：要做好施工采购规划，通过生产要素的优化配置、合理使用、动态管理有效控制实际成本",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]