[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118249,789,1,"单选题","施工项目降低成本的指导文件及设立目标成本的依据，指的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工成本预测",false,{"key":16,"text":17,"correct":14},"B","施工成本分析",{"key":19,"text":20,"correct":21},"C","施工成本计划",true,{"key":23,"text":24,"correct":14},"D","施工成本核算","2021\u002F2020教材P98页 施工成本计划是以货币形式编制施工项目在计划期内的生产费用、成本水平、成本降低率以及为降低成本所采取的主要措施和规划的书面方案，它是建立施工项目成本管理责任制、开展成本控制和核算的基础，它是该项目降低成本的指导文件，是设立目标成本的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]