[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118243,789,1,"单选题","施工成本管理的任务和环节中，（）是对成本计划的最后检验，它所提供的成本信息又将成为下一个施工项目成本预测和决策提供基础资料。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工项目成本控制",false,{"key":16,"text":17,"correct":18},"B","施工项目成本核算",true,{"key":20,"text":21,"correct":14},"C","施工项目成本计划",{"key":23,"text":24,"correct":14},"D","施工项目成本分析","2021\u002F2020教材P100页 施工成本管理的任务和环节中，成本核算是对成本计划的最后检验，它所提供的成本信息又将成为下一个施工项目成本预测和决策提供基础资料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]