[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118242,789,1,"单选题","( )是对成本计划是否实现的最后检验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本预测",false,{"key":16,"text":17,"correct":14},"B","成本评审",{"key":19,"text":20,"correct":14},"C","成本概算",{"key":22,"text":23,"correct":24},"D","成本核算",true,"2021\u002F2020教材P100页 施工成本管理的每一个环节都是相互联系和相互作用的。成本预测是成本决策的前提，成本计划是成本决策所确定目标的具体化。成本计划控制则是对成本计划的实施进行控制和监督，保证决策的成本目标的实现，而成本核算又是对成本计划是否实现的最后检验，它所提供的成本信息又对下一个施工项目成本预测和决策提供基础资料。成本考核是实现成本目标责任制的保证和实现决策目标的重要手段。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]