[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118239,789,1,"单选题","下列施工成本管理的措施中，属于组织措施的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定最佳的施工方案",false,{"key":16,"text":17,"correct":14},"B","对施工成本管理目标进行风险分析，并制定防范性对策",{"key":19,"text":20,"correct":14},"C","选用合适的合同结构",{"key":22,"text":23,"correct":24},"D","加强施工定额管理和施工任务单管理，控制活动和物化活动的消耗",true,"2021\u002F2020教材P100页 组织措施的另一方面是编制施工成本控制工作计划，确定合理详细的工作流程。..........加强施工定额管理和施工任务单管理，控制活动和物化活动的消耗；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]