[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118236,789,1,"单选题","施工成本管理的每一个环节都是相互联系和相互作用的，()是成本决策所确定目标的具体化。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本计划",true,{"key":16,"text":17,"correct":18},"B","成本控制",false,{"key":20,"text":21,"correct":18},"C","成本预测",{"key":23,"text":24,"correct":18},"D","成本考核","2021\u002F2020教材P100页 施工成本管理的每一个环节都是相互联系和相互作用的。成本计划是成本决策所确定目标的具体化",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]