[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118235,789,1,"单选题","发包人应在签发最终结清支付证书后的( )天内，按照最终结清支付证书列明的金额向承包人支付最终结清款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","14",false,{"key":20,"text":21,"correct":18},"C","21",{"key":23,"text":24,"correct":18},"D","28","2021\u002F2020教材P93 发包人应在颁发最终结清证书后“7”天内完成支付。。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]