[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118233,789,1,"单选题","某混凝土工程，招标文件中估计工程量为4000m3合同约定的综合单价为600元\u002Fm3，当实际工程量超过清单工程量15%时可调整单价，调整系数为0.8。工程结束时实际工程量为4800m3，则该混凝土工程的结算价款是()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","240.0",false,{"key":16,"text":17,"correct":14},"B","270.0",{"key":19,"text":20,"correct":21},"C","285.6",true,{"key":23,"text":24,"correct":14},"D","192.0","2021\u002F2020教材P78页 工程量偏差，原文是(1)对于任一招标工程量清单项目，如果因本条规定的工程量偏差和工程变更等原因导致工程量偏差超过15%，调整的原则为：当工程量增加15%以上时，其增加部分的工程量的综合单价应予调低；当工程量减少15%以上时，减少后剩余部分的工程量的综合单价应予调髙。合同约定范围内的工程款为：4000×(1+15%)×600=4600×600-2760000元；超过15%后部分工程量的工程款为：(4800-4600)×600×0.8-96000元；则土方工程款合计=2760000+96000=2856000元=285.6万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]