[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118226,789,1,"单选题","工程施工过程中，下列因不可抗力事件导致的人员伤亡、财产损失及其费用增加，由承包人承担的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程所需清理、修复费用",false,{"key":16,"text":17,"correct":14},"B","合同工程本身的损害",{"key":19,"text":20,"correct":21},"C","承包人人员伤亡",true,{"key":23,"text":24,"correct":14},"D","待安装设备的损害","2021\u002F2020教材P86页 《标准施工掊标文件》中合同条款规定的可以合理补偿承包人索赔的条款表2Z102044。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]