[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118224":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118224,789,1,"单选题","某基础土方工程，招标文件中估算工程量为4000m3，合同中约定，土方单价为5元／m3，当实际工程量超过估算工程量15%时，调整单价为4元／m3，工程结束时实际完成土方工程量为4900m3，则土方工程款为()元",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20000",false,{"key":16,"text":17,"correct":18},"B","24200",true,{"key":20,"text":21,"correct":14},"C","29350",{"key":23,"text":24,"correct":14},"D","27500","2021\u002F2020教材P84页 实际完成土方工程量49004000×（1+15%）=4600m3，单价需调整：土方工程款=4600×5+(4900-4600)×4=24200元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]