[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118220,789,1,"单选题","由于承包人原因未在约定的工期内竣工的，则对原约定竣工日期后继续施工的工期，在使用价格调整公式是，应采用原约定竣工日期与实际竣工日期的两个价格指数()作为现行价格指数。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","较低",true,{"key":16,"text":17,"correct":18},"B","较高",false,{"key":20,"text":21,"correct":18},"C","平均值",{"key":23,"text":24,"correct":18},"D","的和","2021\u002F2020教材P80页 由于承包人原因未在约定的工期内竣工的，则对原约定竣工日期后继续施工的工期，在使用价格调整公式是，应采用原约定竣工日期与实际竣工日期的两个价格指数中较低的一个作为现行价格指数。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]