[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118218,789,1,"单选题","根据《标准施工招标文件》，招标工程以()为基准日，其后国家的法律、法规、规章和政策发生变化引起工程造价增减变化的，发承包双方应当按照相关规定调整合同价款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标截止日前28天",true,{"key":16,"text":17,"correct":18},"B","合同签订前28天",false,{"key":20,"text":21,"correct":18},"C","招标截止日前28天",{"key":23,"text":24,"correct":18},"D","合同备案前28天","2021\u002F2020教材P77页 招标工程以投标截止日前28天，非招标工程以合同签订前28天为基准日",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]