[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118214,789,1,"单选题","根据竣工结算的计算原则，计日工应按（）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计价规范相关规定",false,{"key":16,"text":17,"correct":14},"B","合同约定的金额",{"key":19,"text":20,"correct":21},"C","发包人实际签证确认的事项",true,{"key":23,"text":24,"correct":14},"D","发承包人双方签证确认的金额","2021\u002F2020教材P92页 (3)其他项目应按下列规定计价： ①计日工应按发包人实际签证确认的事项计算；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]