[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118212,789,1,"单选题","某合同工程由于设计变更，发生现场签证事项，承包人为了赶工，在未经发包人现场确认和书面同意的情况下便擅自施工，由此产生的费用由（）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","承发包双方共同",{"key":23,"text":24,"correct":14},"D","设计单位","2021\u002F2020教材P87页 若发包人未签证同意，承包人施工后发生争议的，责任由承包人自负",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]