[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118209":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118209,789,1,"单选题","施工期间，如果承包人未经发包人核对即自行采购新材料，采购完成后才报发包人确认调整合同价款的，则（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人应按承包人采购材料予以批准",false,{"key":16,"text":17,"correct":14},"B","发包人全部不予批准",{"key":19,"text":20,"correct":21},"C","发包人不同意，则不作调整",true,{"key":23,"text":24,"correct":14},"D","发包人部分予以批准","2021\u002F2020教材P81页 如果承包人未经发包人核对即自行采购材料，再报发包人确认调整合同价款的，如发包人不同意，则不作调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]